CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Mark (✓) against the correct answer
12 workers take 4 hours to complete a job. How long would it take 15 workers to complete the job?

(a) 2 hrs 40 min
(b) 3 hrs 12 min
(c) 3 hrs 24 min
(d) 3 hrs 30 min

Open in App
Solution

Time taken by 12 workers to complete the job = 4 h
Time taken by 1 worker to complete the job = 4×12 h
Time taken by 15 workers to complete the job = 4×1215 = 3 h 12 min

Hence, 15 workers will complete the job in 3 h 12 min.

The correct option is (b).

flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to speed
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon