Question

Neena, Meena and Tina can do a piece of work in 4 days, 8 days and 6 days respectively. Neena and Tina work together for 1 day and then Neena leaves and Tina is joined by Meena to complete the work. How long does Tina work(in hours)?

Open in App
Solution

Work done by Neena in 1 day W4

Work done by Meena in 1 day W8

Work done by Tina in 1 day W6

Now, work done in 1 day by Neena and Tina W4+W6=5W12

Then Neena Leaves and tina is joined by Meena

5W12+x(W8+W6)=W512+x(724)=1x(724)=1512x(724)=712x=2 days

Hence, tina Works for 2+1=3 days