P,Q and R can do a piece of work in 10,20 and 30 days respectively. In how many days can Q do the work if he is assisted by P and R on every fourth day?
A
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
14 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
16 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B12 days Q′s3 days work =(120×3)=320
(P+Q+R)′s1 day work =(110+120+130)=1160
Work done in 4 days =(320+1160)=2060=13
Now, 13 work is done in 4 days. ∴ Whole work will be done in 4×3=12 days