wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

P, Q and R can do a piece of work in 10, 20 and 30 days respectively. In how many days can Q do the work if he is assisted by P and R on every fourth day?

A
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
14 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
16 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Join BYJU'S Learning Program
CrossIcon