P, Q, R, S, and T are the 5 activities along the unique critical path of an AOA network of activities. Their characteristics are as under

ActivityPQRSTExpected duration (days)8712156Standard deviation (days)33452

What is the possible range of project duration (in days)?

A
28.12 to 57.91
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
24.19 to 71.81
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
34.23 to 47.21
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
25.50 to 60.51
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 24.19 to 71.81
Project duration =8+7+12+15+6=48 days

σproject=32+32+42+52+22

=7.937 days

Possible range of project duration =Te±3σ

=(483×7.937).(48+3×7.937)

=(24.189).(71.811)

=(24.189,71.811)

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Mathematical Application of Correlation
STATISTICS
Watch in App
Join BYJU'S Learning Program
CrossIcon