Ram and Shyam work on a job together and finish 60% of it. Ram takes leave after 4 days and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?
A
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
10 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
12.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!