Question

Ram and Shyam work on a job together and finish 60% of it. Ram takes leave after 4 days and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?


A

6 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

8 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

10 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D

12.5 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!