Question

Shwetha takes 6 days less than the number of days taken by Ankitha to complete a piece of work. If both Shwetha and Ankitha together can complete the same work in 4 days, in how many days will Ankitha alone complete the work?

Open in App
Solution

Let the number of days Ankitha takes to complete the work be x.

It is given that Shwetha takes 6 days less than the number of days taken by Ankitha to complete a piece of work, therefore, the number of days Shwetha takes to complete the work is (x6).

Now, amount of work done by Ankitha in 1 day is 1x and amount of work done by Shwetha in 1 day is 1x6.

It is also given that both Shwetha and Ankitha together can complete the same work in 4 days, therefore, amount of work done by both in 1 day is 14.

Thus, we have

1x+1x6=14x6+xx(x6)=142x6x26x=14x26x=4(2x6)x26x=8x24x26x8x+24=0x214x+24=0x212x2x+24=0x(x12)2(x12)=0(x2)=0,(x12)=0x=2,x=12

x=2, can not be taken because x6 will become 4
thus, x=12.

Hence, the number of days Ankitha alone takes to complete the work is 12

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Solving QE by Factorisation
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon