Sixty-four men working 8 hours a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day do they need to work in order to achieve the target?

A
11
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
13
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
15
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 15
Total work (in terms of man-hours) = 64×8×50.4
Work remaining (in terms of man-hours) = 64×8×50.4×0.6
Working hours per day needed to complete remaining work in 4 days
= 64×8×50.4×0.6×164×4
= 15 hours.

Alternate Approach:
MenWorking HoursDayWork done648540%64n(say)460%
40% work in 40 hours 60% work in 60 hours.
Hence, working hours
=604=15 hours

flag
Suggest Corrections
thumbs-up
12
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon