The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship "X < Y, Z" means that X is the predecessor of activities Y and Z. The time to complete the activities along the critical path is ____ weeks.

Activity Duration (Weeks) Precedence Relationship
A 5 A < B, C, D
B 7 B < E, F, G
C 10 C < I
D 6 D < G
E 3 E < H
F 9 F < I
G 7 G < I
H 4 H < I
I 2 ....

A
21
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
23
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
17
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
25
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 23


So critical path is A - B - F - I

Critical path duration = 23 weeks

Correct option is (d).

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon