The are 16 workers working to construct a wall and it will take 48 hours to build it. But due to some accident, 4 workers got injured and could not work. Now, the contractor wants the wall to be built in 32 hours. How many more workers are required to complete the job?
8
Given that 16 workers take 48 hours to build the wall. If the time is reduced to 30 hours, then let the number of workers required be y.
16×48=y×32
⇒y=24
Since 4 workers got injured in an accident and could not work, the remaining number of workers at the site is
16−4=12
Thus, the additional number of workers required will be
24−12=12.