The expected time (te) of a PERT activity in terms of optimistic time (to), pessimistic time (tp) and most likely time (tl) is given by
A
te=to+4tp+tl3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
te=to+4tp+tl6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
te=to+4tl+tp6
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
te=to+4tl+tp3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is Cte=to+4tl+tp6 The expected time (to) of PERT activity in terms of optimistic time (to), pessimistic time (tp) and most likely time (tl) is given by,