The flow net of activities of a project is given in the following figure. The duration of activities are indicated along the arrows.
The critical path of the activities is along
A
1 - 3 - 5 - 7 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1 - 2 - 4 - 7 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1 - 3- 5 - 6 - 8 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1 - 3- 6 - 8 - 9
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D 1 - 3- 6 - 8 - 9 The critical path should have maximum duration. 1−2−4−7−96+9+14+12=411−3−5−7−98+9+14+12=431−3−5−6−8−98+9+0+13+15=451−3−6−8−98+10+13+15=46
Maximum duration is for path 1−3−6−8−9, so this is the critical path.