CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

The flow net of activities of a project is given in the following figure. The duration of activities are indicated along the arrows.

The critical path of the activities is along

A
1 - 3 - 5 - 7 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1 - 2 - 4 - 7 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1 - 3- 5 - 6 - 8 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1 - 3- 6 - 8 - 9
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 1 - 3- 6 - 8 - 9
The critical path should have maximum duration.
124796+9+14+12=41135798+9+14+12=431356898+9+0+13+15=45136898+10+13+15=46
Maximum duration is for path 13689, so this is the critical path.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Decentralisation
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon