CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

The management of a college decides to paint the college auditorium and observes that 16 workers can paint it in 10 days. The number of workers needed to complete the work in 4 days is 36.


A

True

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

False

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is B

False


As the number of workers increases, the number of days required for the work to be completed decreases. This is an inverse proportion condition.

Let the required number of days be n

16×10=4×n

n=40

So, 40 workers are required to finish the work in 4 days.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Variation
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon