Question

The network diagram for a project is shown below. The duration of activites is shown in the brackets of network diagram. The critical path for the project is


A
1 - 2 - 4 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1 - 3 - 7 - 8 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
None of these
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
1 - 3 - 5 - 9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C None of these

Critical path is 1 - 2 - 6 - 8 - 9