The percentage loss of prestress due to anchorage slip of 3 mm in a concrete beam of length 30 m which is post-tensioned by a tendon with an initial stress of 1200N/mm2 and modulus of elasticity equal to 2.1×105N/mm2, is
A
0.0175
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0.175
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1.75
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
17.5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 1.75 Loss of prestress =Δll×Eb=330×103×2.1×105=21N/mm2
Initial stress =1200N/mm2 ∴ Loss of prestress =211200×100=1.75%