The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are

Activity Predecessors Duration (days)
a - 2
b - 4
c a 2
d b 3
e c 2
f c 4
g d, e 5

A
1 and 4
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
2 and 3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3 and 1
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0 and 4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 1 and 4


Total float =Lj(Ei+tijE)

Total float for activity: e = 7 - 2 - 4 = 1

Total float for activity: f = 12 - 4 - 4 = 4

Points to Remember:

Total float represents the amount of time by which a particular activity can be delayed without delaying the project completion time.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Functional Groups and Nomenclature
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon