The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are
Activity | Predecessors | Duration (days) |
a | - | 2 |
b | - | 4 |
c | a | 2 |
d | b | 3 |
e | c | 2 |
f | c | 4 |
g | d, e | 5 |