The project given below follows PERT analysis whose expected duration of completion is 8 days. The pessimistic time for activity AB of the project will be ________ days.
5
Open in App
Solution
The correct option is A 5
tE,AB=x+2+4×46=x+186days
tE,BC=3+4×4+66=256days
∴ Total expected time of completion of project = 8 days