wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

The project given below follows PERT analysis whose expected duration of completion is 8 days. The pessimistic time for activity AB of the project will be ________ days.


  1. 5

Open in App
Solution

The correct option is A 5

tE,AB=x+2+4×46=x+186days

tE,BC=3+4×4+66=256days

Total expected time of completion of project = 8 days

Expected project duration x+186+256=(x+436)days

x+436=8

x=5days


flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Successors of Shivaji
HISTORY
Watch in App
Join BYJU'S Learning Program
CrossIcon