There are four jobs to be completed. Each job must go through machines M1,M2,M3 in the order M1−M2−M3. Processing time in hours is given below. Determine idle time for Machine M1
Jobs | A | B | C | D |
M1 | 5 | 8 | 7 | 3 |
M2 | 6 | 7 | 2 | 5 |
M3 | 7 | 8 | 10 | 9 |
Job | M1 | M1 | M2 | M2 | M3 | M3 |
Time In | Time Out | Time In | Time Out | Time In | Time Out | |
D | 0 | 3 | 3 | 8 | 8 | 17 |
C | 3 | 10 | 10 | 12 | 17 | 27 |
A | 10 | 15 | 15 | 21 | 27 | 34 |
B | 15 | 23 | 23 | 30 | 34 | 42 |
D | C | A | B |
Jobs | A | B | C | D |
G=M1+M2 | 11 | 15 | 9 | 8 |
H=M1+M2 | 13 | 15 | 12 | 14 |