Three activities A, B, and C are to be executed in the sequence of A-B-C. The relationship between time (in days) and normal cost (in Rs.) is given in the following table
The total direct cost when the project duration is 35 days is _______
Open in App
Solution
Project duration = 44 days
Total direct cost = 2500 /-
To reduce the project duration by 9 days we need to crash minimum cost slope
Original Network:
Project duration = 44 days
Total direct cost = 2500 /-
To reduce the project duration by 9 days we need to crash the minimum cost slope
Critical Activity:
Project duration = 35 days
Total direct cost = 3200 /-