wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Three activities A, B, and C are to be executed in the sequence of A-B-C. The relationship between time (in days) and normal cost (in Rs.) is given in the following table


The total direct cost when the project duration is 35 days is _______

Open in App
Solution

Project duration = 44 days
Total direct cost = 2500 /-
To reduce the project duration by 9 days we need to crash minimum cost slope


Original Network:

Project duration = 44 days
Total direct cost = 2500 /-
To reduce the project duration by 9 days we need to crash the minimum cost slope

Critical Activity:

Project duration = 35 days
Total direct cost = 3200 /-

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Deducing a Formula for Compound Interest concept video
Watch in App
Join BYJU'S Learning Program
CrossIcon