CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
85
You visited us 85 times! Enjoying our articles? Unlock Full Access!
Question

Tick (✓) the correct answer:
A can do a piece of work in 20 days which B alone can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
(a) 3 days
(b) 5 days
(c) 7 days
(d) 11 days

Open in App
Solution

(b) 5 days

A can complete the work in 20 days.Work done by A in 1 day=120B can complete the work in 12 days.Work done by B in 1 day=112In 9 days, B completes 912, i.e., 34 of the work and leaves 1-34, i.e., 14 of the work undone. Time taken by A=14÷120=14×20=5 days

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon