A can do a piece of work in 25 days, which B alone can do in 20 days. A started the work and was joined by B after 10 days. The work lasted for
(a) 1212 days
(b) 15 days
(c) 1623 days
(d) 14 days
A can do the piece of work in 25 days.
The part of the work done by A in 1 day=125
B can do the same work in 20 days.
The part of the work done by B in 1 day =120
Since, A worked as alone 10 days.
So, the part of the work done by A in 10 days =1025=25
⇒ The remaining work =1−25=35---(1)
The part of the work done by A+B =125+120
=4+5100
=9100
Hence, The part of the work done by A+B=9100
Since, the remaining part of the work is 35
⇒ Time taken to finish the remaining work if they work together
=35÷9100
=35×1009
=10015
=61015
=623
So they will finish the remaining work in 623 days.
Here A already worked in 10 days.
So, Total number of days to finish the work =(10+623) days
=(10+6+23) days
=1623 days
Hence, Option C is correct.