Question

A can do a piece of work in 15 days. B is 50% more efficient than A. B can finish the total work in
(a) 10 days
(b) 712 days
(c) 12 days
(d) 1012 days

Open in App
Solution

Correct option is (a). 10 days
Amount of work done by A in one day =115 units.

Since, B is 50% more efficient than A, therefore,

Amount of work done by B in one day =115+12×115=115×32=110 units.

Thus, time taken to complete the total work =1÷110

=10 days