CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 25 days, which B alone can do in 20 days. A started the work and was joined by B after 10 days. The work lasted for
(a) 1212 days
(b) 15 days
(c) 1623 days
(d) 14 days

Open in App
Solution

A can do the piece of work in 25 days.

The part of the work done by A in 1 day=125

B can do the same work in 20 days.

The part of the work done by B in 1 day =120

Since, A worked as alone 10 days.

So, the part of the work done by A in 10 days =1025=25

The remaining work =125=35---(1)

The part of the work done by A+B =125+120

=4+5100

=9100

Hence, The part of the work done by A+B=9100

Since, the remaining part of the work is 35

Time taken to finish the remaining work if they work together

=35÷9100

=35×1009

=10015

=61015

=623

So they will finish the remaining work in 623 days.

Here A already worked in 10 days.

So, Total number of days to finish the work =(10+623) days

=(10+6+23) days

=1623 days

Hence, Option C is correct.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon