CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
161
You visited us 161 times! Enjoying our articles? Unlock Full Access!
Question

Tick (✓) the correct answer:
A does 20% less work than B. If A can finish a piece of work in 712 hours, then B can finish it in
(a) 5 hours
(b) 512 hours
(c) 6 hours
(d) 612 hours

Open in App
Solution

(c) 6 hours

Time taken by A to finish the piece of work=712 hours=152 hoursWork done by A in 1 hour=215Let B take x hours to finish the work.Work done by B in 1 hours=1xA can work 20%less than B, or A can do 45 of B's work.Now, 451=2151x45=2x15x=15×45×2=6 hours

flag
Suggest Corrections
thumbs-up
6
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Arithmetic Mean and Range
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon