Question

Today is day 22 on the production control calendar, and four jobs are on order as shown:

Job Due dates Working days remaining
A 28 8
B 26 2
C 24 2
D 30 12

With the critical ratio scheduling technique, the jobs would be assigned in order of

A
B-C-D-A
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
B-C-A-D
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
D-A-C-B
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
A-B-C-D
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C D-A-C-B
Job Time remaining
(Due date - Today date)
Work days
reaining
Critical ratio
=Time remainingWork remaining
Priority
A 28-22=6 8 0.75 2
B 26-22=2 2 2 4
C 24-22=2 2 1 3
D 30-22=8 12 0.67 1

With this critical ratio, jobs would be assigned in the order of DACB.

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Three Sets Venn Diagram
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon