Today is day 22 on the production control calendar, and four jobs are on order as shown:
Job | Due dates | Working days remaining |
A | 28 | 8 |
B | 26 | 2 |
C | 24 | 2 |
D | 30 | 12 |
Job | Time remaining (Due date - Today date) |
Work days reaining |
Critical ratio =Time remainingWork remaining |
Priority |
A | 28-22=6 | 8 | 0.75 | 2 |
B | 26-22=2 | 2 | 2 | 4 |
C | 24-22=2 | 2 | 1 | 3 |
D | 30-22=8 | 12 | 0.67 | 1 |