Twenty five workers were employed to complete a compound wall in 12 days.Five workers left after working for 4 days. The remaining 20 workers completed the work, in how many days the total job was completed?
A
15 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
16 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
14 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
18 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 14 days Total work = Number of workers x Number of days
Therefore, total work =25 workers×12 days.
As it is given that, 25 workers worked for 4 days and then 4 of them left, therefore, let remaining 20 workers worked for y days. Thus, we have: