Two activities A and B are to be done in the given sequence. The variation of direct cost (DC) with possible activity duration (T) (in days) is indicated for each activity as follows.
TDCTDC8121015714917617819521721
What is the increase in total direct cost between a combined duration of 16 days and 13 days?