Two activities A and B are to be done in the given sequence. The variation of direct cost (DC) with possible activity duration (T) (in days) is indicated for each activity as follows.
TDCTDC8121015714917617819521721


What is the increase in total direct cost between a combined duration of 16 days and 13 days?

A
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 7
Normal time for both activities
for A, TNA=8 days
for B, TNB=10 days

Either of the activities can be crashed and the tabular representation of crashing is as follows:
ActivityDirect costsTotal timeTotal costA BA B8 1012 1518277 1014 1517297 914 1716317 814 1915337 714 2114356 717 2113385 721 211242

Increase in direct cost between a combined duration of 16 days and 13 days = 38 - 31 =7

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Deducing a Formula for Compound Interest concept video
Watch in App
Join BYJU'S Learning Program
CrossIcon