Question

X alone can do a piece of work in 5 days. Y can do the same piece of work in 4 days. X and Y are assigned to do the work for Rs 5000. They complete the work in 2 days with the help of Z. How much is to be paid to Z?


Your Answer
A
Rs 750
Your Answer
B
Rs 620
Your Answer
C
Rs 700
Correct Answer
D
Rs 500
Your Answer
E
None of these

Solution

The correct option is D Rs 500
Z's one day work =12(15+14)=104520=520=120
Ratio = 15:14:120=4:5:1
Z=5000×110=500