The correct option is C 40 days
Let the total unit of work be 480 units. (LCM of 30 and 32)
X and Y together complete the work in 30 days.
(X+Y)do=48030=16 units/day
According to the question,
16×6+Y×32=480
Y×32=384
Y=12
Y does =12 units/day.
Y alone can complete the work =48012=40 days.