12 men, working 8 hours a day, complete a piece of work in 10 days. To complete the same work in 8 days working 15 hours a day, the number of men required is
The correct option is A 8
Letnumberofmen(m1)=12
numberofhours(h1)=8
numberofdays(d1)=10
numberofmen(m2)=x
numberofhours(h2)=10
numberofdays(d2)=8
Accordingtogivenproblem
m2×d2×h2=m1×d1×h1
⇒x×8×10=12×8×10
⇒x=8