CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
33
You visited us 33 times! Enjoying our articles? Unlock Full Access!
Question

A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. The total work will be completed in :

A
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
13 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1357 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1334 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 1334 days
On the first day A complete; 116th of work.
On the second day B complete; 112th of work.
Therefore in 2 days =116+112=748 of the work.

In 12 days they complete 6×748 of the work =4248 of the work
Remaining work =648
On the 13th day A completes 348 of the work.
Remaining work is 348 now B completes work in (348)(112)=34 day.
Whole work completed in 1334days.
Hence, the answer is 1334.



flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Properties
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon