CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

M and N alone can so a work in 21 and 42 days respectively.In how many days they can complete the work, if they work on alternate days?

A
14
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
28
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
42
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
35
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 28
Work completed by M in one day =121.

Work completed by N in one day =142.

So, amount of work completed in every two days =121+142=342=114

Let 2 days=1 time unit.

Number of time units required for the work to complete 1(114)=14.

Number of days required to complete the work =14×2=28 days. [B]

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Variations
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon