The correct option is B 12 days
(A+B)'s 1 day's work (115+110)=16
Work done by A and B in 2 days =(16×2)=13
Remaining work =(1−13)=23
Now, 115 work done by A in 1 day.
∴ 23 work will be done by A in (15×23)=10 days.
Hence, the total time taken =(10+2)=12 days.