A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days. B joined him till the completion of the work. How long did the work last.?
A
10 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
20 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
15 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is D10 days A's one days' work =120.
B's one days' work =112.
Work done by A in 4 days =420=15. Remaining work =1−15=45
(A+B)'s 1 days' work =120+112=215 ∴ Number of days to do the remaining work =45÷212=45×152=6 days ∴ Total number of days taken in the completion of work =6+4=10 days.