The correct option is
B 11 days
A's 1 day's work =125
Similarly, B's 1 day's work =120
A's and B's together 1 day's work
125+120=4100+5100=4+5100=9100
Their 5 day's work together = 5 x 1 day's work
1−45100=100100−45100=100−45100=55100
Now, this remaining work is done by B.
Let B takes x days to complete it.
120×x=55100⇒x=55100×20⇒x=555⇒x=11
Hence, B will finish the remaining work in 11 days.