A can finish a piece of work in 14 days. The same work can be finished by B in 21 days. They start the work together, but 3 days before the completion of the work, A leaves.
What is the total number of days required to complete the work, had both of them worked together?
B’s 3 days’ work =(121×3)=17
Remaining work =(1−17)=67
(A+B)’s 1 day’s work =(114+121)=542
Now, 542 work is done by A and B in 1 day.
∴ 67 work is done by A and B in (425×67)=365 days
Hence, total time taken =(3+365) days = 1015 days