wiz-icon
MyQuestionIcon
MyQuestionIcon
2
You visited us 2 times! Enjoying our articles? Unlock Full Access!
Question

A certain number of men can finish a price of work in 100 days .If there were 10 men less ,it would take them 10 days more to finish the work. How many men were there originally?

Join BYJU'S Learning Program
CrossIcon