A contractor employed 210 men to build a house in 60 days. After 12 days, he was joined by 70 more men. In how many days will the remaining work be finished?
A
35days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
36days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
38days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
40days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B36days
Given that,
Let the total work to be done =1
210 men build a house in 60 days
each man 1 day work =1210×60
After 12 days,
Total work done by 210 workers in 12 days
=1210×60×210×12=15
70 extra workers joined the work now
total workers =280
Remaining work =1−15=45 .............(1)
Let the remaining work finished in next X days
Total work done by 280 workers in X days =1210×60×280×X ..................(2)