A contractor employed 210 men to build a house in 60 days. After 12 days, he was joined by 70 more men. In how many days will the remaining work be finished?
A
35
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
36
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
38
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
40
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A 36 So, 210 men employed for 60 days to complete work.