Question

A linear project is split into six identical activities, each having a, m and b durations of 4, 8 and 10 days, which results in the standard deviation of the duration for the complete project being X1 days. As an alternative attempt at project planning, the earlier-split six activities are clubbed as (1st and 2nd), (3rd and 4th) and (5th and 6th), thus needing to consider only three (now-modified) activities; and the standard deviation of the duration for the complete project is now reported asX2 days. What will be the ratio X2X1?

A
56
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
23
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
76
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 1
Case I :

Cast II :

After clubbing the activities



Std. deviation of individual activities

=1046=1 (before clubbing)

Std. deviation of whole project in case-I

Std. deviation of individual activities after clubbing

=12+12=2

Std. deviation of whole project in case-II

(X2)=(2)2+(2)2+(2)2=6

X2X1=66=1

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
HISTORY
Watch in App
Join BYJU'S Learning Program
CrossIcon