wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A,B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days A left. Then B and C together completed the work in 10 more days. A alone could complete the work in :

A
15 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
16 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
25 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
50 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 25 days
Work done by A,B,C in 1 day is 110
After 4 days the work left is 610
Work done by B,C in 1 day is 6100

So, Work done by A in one day is 1106100=125

so A takes 25 days to complete the work.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Ratio and Proportion
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon