Let x be the number of days in which one man can complete the work.
Let y be the number of days in which one boy can complete the work.
In one day a man can do 1xth work and a boy does 1yth work.
Now 2 men and 7 boys can complete the work in 4 days. Hence they can complete 14th of the work in one day. Thus we obtain
2x+7y=14 ..............(1).
Again 4 men and 4 boys together complete the work in 3 days. Hence they can complete 13rd of the work in a day. Thus we also get
4x+4y=13.........(2)
Multiply (1) by 2 and subtract (2) from it, you get
4x+14y−4x−4y=24−13.
This reduces to 10y=16. Hence y=60. From equation (2) we get
4x=13−4y=13−460=13−115=415.
Hence x=15.
Thus, one man can complete the work in 15 days and one boy can do the work in 60 days.