CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.

Activity Predecessors Duration (days)
a - 3
b a 4
c a 5
d a 4
e b 2
f d 9
g c, e 6
h f, g 2

The critical path for the project is

A
a-c-g-h
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
a-b-e-g-h
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
a-b-c-f-h
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
a-d-f-h
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D a-d-f-h


Various paths:

1. abegh - 17 days

2. acgh - 16 days

3. adfh - 18 days

a-d-f-h is the critical path.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Integration of the French and Portuguese Colonies
HISTORY
Watch in App
Join BYJU'S Learning Program
CrossIcon