For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
Activity | Predecessors | Duration (days) |
a | - | 3 |
b | a | 4 |
c | a | 5 |
d | a | 4 |
e | b | 2 |
f | d | 9 |
g | c, e | 6 |
h | f, g | 2 |