CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

How to Calculate Early Start and Early Finish in CPM?


Open in App
Solution

The formula used for calculating the Early start and Early finish in CPM is as follows:

Early Start of the activity = Early Finish of predecessor activity + 1

Early Finish of the activity = Activity duration + Early Start of activity – 1

Stay connected to BYJU’S for more such interesting questions and answers.

Also see:


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Consistency Test and Setting Time
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon