How to Calculate Early Start and Early Finish in CPM?


Open in App
Solution

The formula used for calculating the Early start and Early finish in CPM is as follows:

Early Start of the activity = Early Finish of predecessor activity + 1

Early Finish of the activity = Activity duration + Early Start of activity – 1

Stay connected to BYJU’S for more such interesting questions and answers.