Q4) A contractor employs 280 men to complete a work in 10 days. But after 3 days, it was found that only 1/4th of the work was done. How many additional men are required to finish the work on time?
A
(a) 360
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
(b) 120
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
(c) 140
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
(d) 80
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D (d) 80 Ans:4)(d)Sol: Given, (280 ×m ×3) = (1/4)W; Let, 'n' is the new number of men. (n × m × 7) = (2/4)W; (280 ×m ×3)/ (n × m × 7) =(1/4)/(3/4) n=360; Additional number of men= 80