CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Sunil takes 5 days more than Anil to complete a certain work. 4 day after starting the work, Anil left the work. The remaining work was done by Sunil in 5 days. Find how many days each will take to complete the work.

Open in App
Solution

Let Anil takes x number of days to complete the work
1 day =1x of the work.
Sunil takes 5 more days than Anil to complete the work.
x+5 days
1 day =1(x+5) of the work
Together:
1 day =1x+1x+5
1 day =(x+5+x)x(x+5)
1 day =(2x+5)(x2+5x) of work done
To find 4 days of work done:
1 day =(2x+5)(x2+5x)
4 days=4(2x+5)(x2+5x)
4 days =(8x+20)(x2+5x) of work done
To find the amount of work left to be done:
Work left =1(8x+20)(x2+5x)
Work left =(x2+5x8x20)(x2+5x)
Work left =(x23x20)(x2+5x)
Solving for x:
Give that Anil needs 5 days to complete the rest of the work
(x23x20)(x2+5x)×(x+5)
=(x23x20)x
5x23x20=5x
x²8x20=0
(x10)(x+2)=0
x=10 or x=2 (Rejected, number of days cannot be negative)
To find the number of days each take to complete the work
Anil =x=10 days
Sunil =x+5=10+5=15 days
Thus, Anil takes 10 days and Sunil takes 15 days to complete the work.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon