There are 5 jobs in waiting for getting processed on a machine,
Job | Processing Time (Days) |
Due date |
J1 J2 J3 J4 J5 |
5 5 6 2 2 |
7 8 10 7 3 |
Job | J1 | J2 | J3 | J4 | J5 |
STR (Di−Pi) |
2 | 3 | 4 | 5 | 1 |
Job | Processing Time Pi |
Due date Di |
Flow time Fi |
Tardiness Fi−Di |
J5 J1 J2 J3J4 |
2 5 5 6 2 |
3 7 8 10 7 |
2 2+5 = 7 7+5=12 12+6=18 18+2=20 |
0 0 12-8=4 18-10=8 20-7=13 |