wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 15 days. B is 50% more efficient than A. B can finish the total work in
(a) 10 days
(b) 712 days
(c) 12 days
(d) 1012 days

Open in App
Solution

Correct option is (a). 10 days
Amount of work done by A in one day =115 units.

Since, B is 50% more efficient than A, therefore,

Amount of work done by B in one day =115+12×115=115×32=110 units.

Thus, time taken to complete the total work =1÷110

=10 days


flag
Suggest Corrections
thumbs-up
6
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon