A can do a piece of work in 40 days and B can do the same piece of work in 60 days. A and B started the work together, in the first 15 days A worked with 50% of his efficiency and in the next 15 days B worked with 50% of his efficiency. In how many days does the remaining work will be completed if both of them work with their full efficiencies?
15*(1/80+1/60) + 15*(1/120+1/40) + x*(1/40+1/60) = 1
X= 3/2 = 1.5