A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work?
A can finish a piece of work in =15 days
B can finish a piece of work in =10 days
∴ A′s 1 day work =115
B′s 1 day work =110
(A+B)′s 1 day work =115+110
=2+330=530=16
(A+B)′s 2 days work =16×2=13
Remaining work which will be done by A alone
=1−13=3−13=23 [Whole work is considered as 1]
∴ A can finish 1 work in =15 days
A can finish 23 work in =15×23 days.
=303 days =10 days.