A can do a piece of work in 15 days. B is 50% more efficient than A. B can finish the total work in(a) 10 days(b) 712 days(c) 12 days(d) 1012 days
A can do a piece of work in 15 days. 13 is 50% more efficient than A. B can finish it in
(a) 10 days
(b) 712 days
(c) 12 days
(d) 1012days
A can do a piece of work in 25 days, which B alone can do in 20 days. A started the work and was joined by B after 10 days. The work lasted for(a) 1212 days(b) 15 days(c) 1623 days(d) 14 days